Concrete price per cubic metre is only one line in a pour budget. Delivery conditions, minimum loads, pumping, reinforcement, formwork, labour, finishing and waste can matter as much as the concrete itself.
Written by: Kaleem Afzal Khan
Start with volume, not price
Measure the concrete quantity first. For a rectangular slab:
A 6 m × 4 m slab at 100 mm thick requires 2.4 m³ before allowance. Use the Concrete Calculator to calculate common shapes and add waste.
The six cost buckets
1. Concrete supply
Price varies with mix specification, strength grade, slump, additives and supplier. Structural concrete should be ordered to the project specification rather than a generic cheapest mix.
2. Delivery
Distance, minimum order, waiting time and site access can affect the delivered cost. A small pour may have a higher effective $/m³ because fixed delivery costs are spread over less concrete.
3. Pumping or placement
If the truck cannot discharge directly, pumping or other placement equipment may be needed. Tight urban access, long hose runs or elevated work can alter the placement plan.
4. Formwork and reinforcement
A concrete rate does not include the steel, chairs, formwork, edge boxing or structural detailing unless the quote says so.
5. Labour and finishing
Placement, vibration, screeding, trowelling, curing and specialist finishes need their own allowance.
6. Waste and contingency
A sensible quantity allowance protects against small measurement errors and placement losses. Over-ordering can also create disposal problems, so the allowance should be deliberate rather than arbitrary.
Worked example
At an indicative $425/m³, 2.4 m³ of concrete is $1,020 for the material line alone. Add a 5% quantity allowance and the order quantity becomes 2.52 m³, or about $1,071 at that rate. Delivery, pumping, reinforcement, formwork and labour remain separate.
Bagged mix for small quantities
For very small volumes, bagged premix can be convenient. Use the Concrete Bag Calculator Australia and the guide to 20 kg bags per m³ to compare the arithmetic.
Source
Planning note: Concrete specification, reinforcement and structural requirements should come from project documentation and qualified professionals where applicable.