Concrete Calculators Australia
Calculate concrete quantities for slabs, footings, trenches, post holes and other common building work using metric inputs.
Concrete volume
Concrete Estimator
Calculate cubic metres for slabs, footings, trenches and round post holes, add a waste allowance and optionally convert the result to premix bags using your product yield.
Slabs
Concrete Slab Estimator
Calculate slab area, concrete volume, waste, planning order quantity, perimeter formwork and optional concrete cost.
Which concrete calculator should I use?
For slabs, footings, trenches and post holes, start with the concrete volume calculator to convert measured dimensions into cubic metres. For a slab take-off with area, concrete quantity and perimeter formwork in one place, choose the concrete slab calculator. For small non-structural jobs using a specified bagged product, use the concrete bag calculator and enter the yield in litres per bag printed by the manufacturer rather than assuming every 20 kg bag has the same yield.
Worked example: how much concrete for a 5 m × 4 m slab?
A uniform rectangular slab measuring 5 m long × 4 m wide × 100 mm thick has a theoretical volume of 5 × 4 × 0.10 = 2.00 m³. If a 5% placement and handling allowance is appropriate for the job, the preliminary ordering quantity becomes 2.00 × 1.05 = 2.10 m³. This calculation assumes uniform thickness and does not include thickened edges, beams, trenches or other additional volumes.
For comparison only, a bagged product that produces 10 litres of mixed concrete per bag would require 2.10 × 1,000 ÷ 10 = 210 bags. Such a quantity may be impractical for bagged mixing; compare ready-mix options, placement time and the required concrete specification instead. See how to calculate concrete bags per cubic metre for the yield-based method.
Before ordering in Australia
Confirm the dimensions on drawings, structural concrete strength and exposure requirements, whether the slab has setdowns or thickened sections, access for delivery and placement, and the supplier’s minimum loads and fees. The estimator is for early planning only and does not replace engineering design or a concrete order checked against project drawings.
For smaller jobs using premixed bags, try the Concrete Bag Calculator Australia. More concrete tools will be added for cost, reinforcement and related project planning.